NEC4 Design, Build and Operate Contract
Contents |
[edit] Introduction
NEC4 brings a new addition to the NEC family of contracts: NEC4 Design, Build and Operate Contract (DBO), released in 2017. It has been added to the suite of contracts in response to the increasing demand for contracts extending into the operational phase.
The demand is coming both from UK clients and from international funding agencies, such as the World Bank and the Asian Development Bank (ADB). In 2015, ADB commissioned NEC to draft a consultative DBO contract, the feedback from which has helped to shape the NEC4 version.
It also aligns with the UK government's commitment to 'soft landings', in which designers and constructors are involved with projects at least three years after construction completion to ensure a smoother handover to the operator.
[edit] New and existing assets
The new DBO contract is not only intended for the 'traditional' DBO approach, where the client requires a new facility or asset to be designed, constructed and then operated by a contractor. It is also available for situations where a client wants to have an existing facility or asset operated by the contractor while it is being upgraded or extended.
In such situations, the timing of the design and construction phase would normally be stated by the client, but may be determined by the contractor – which will undertake the work at a point to suit the performance requirements of the overall service.
The new DBO contract provides for option A (priced contract with price list), option C (target contract with price list) and option E (reimbursable contract).
[edit] Focus on operational needs
The contract starts with the operational and service requirements of the client and then integrates the new or replacement asset to reflect the way that the operation has been specified.
Perhaps even more than other contracts, the development of the client's requirements and specification in the scope will be crucial to the understanding, use and success of the contract.
[edit] Greater role for contractor
All the standard NEC provisions for communications, early warning and compensation events are retained along with some other features added in the NEC4 suite.
The management of the work through plans and programmes for the construction and operation phases are still important.
Recognising the greater involvement and responsibility of the DBO contractor in the operational phase, the contract has a lighter touch than some standard NEC design and build options.
[edit] Incentives and productivity
A key issue for the client is identifying and incentivising performance and productivity of the total asset. This may be through any or all of the traditional NEC approaches, including the reduction of payments for poor performance.
The new DBO contract brings incentives and productivity options together into one schedule and requires the client to identify and develop the approaches it wishes to use.
This article was originally published here on 19 June 2017 by ICE. It was written by Ross Hayes, Richard Patterson and Barry Trebes, NEC4 drafters.
--The Institution of Civil Engineers
[edit] Related articles on Designing Buildings Wiki
- Articles by ICE on Designing Buildings Wiki.
- Construction contract.
- Contract conditions.
- Design and build.
- Design build operate (DBO).
- FIDIC.
- ICE Conditions of Contract.
- NEC3.
- NEC4.
- NEC4 Alliance contract.
- NEC4 contract creates a procurement alliance arrangement for all stakeholders.
- NEC4 - legal and insurance aspects.
Featured articles and news
How can digital twins boost profitability within construction?
A brief description of a smart construction dashboard, collecting as-built data, as a s site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure bill oulined
With reactions from IHBC and others on its potential impacts.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.